Resource Hours

Ralph HavardMember for 21 years 9 months
Created
2
1
0
Morning All
Can someone please confirm when i run a report out P6.1 for the remaining resourse hours does it spread it against the current dates or the planned dates?

Kind Regards

Ralph Havard

2 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Ralph,

    Your Remaining Resource Hours always spread in current dates, as long as you did not assign the Future Period Bucket Planning or Resource Curve for each activities.

    Current & Planned dates are similar during updating, however, Planned dates ca be updated manually. Try to display/show the Planned Dates on your column and see what happen.

    Regards,

    Arnold
  2. 0
    Ralph Havard ·
    Thanks Arnold