Importing Activity Code Dictionary

Joel ClarkMember for 17 years 10 months
Created
3
3
0
How do I import an Activiy Code Dictionary in P6.2??

JJ

3 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Joel

    I have moved this thread to the p6 forum - you will get a better response.

    Best regards

    Mike Testro
  2. 0
    Benjamin Mora ·
    In what format is the AC dictionary?

    If it is in P3, then a simple P3 project import will do the trick.

    If it is in Excel, you could copy and paste them in the Dictionary60.xls, SDK Tool. This method is a bit trickier.

  3. 0
    Arnold Puy ·
    Hi Joel,

    If it is in P6 to P6, open the two projects and go to Activitiy Codes, simply copy and paste.

    HTH.

    Regards,

    Arnold