P6; Resource Usage Spreadsheet
In the Open Standard
Abeer MahmoudMember for 18 years 3 months
- Created
- 2
- 4
0
• During May:
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 500hrs
3- remaining units = 600
4- Required/downtime units = 1 - (2 + 3) = 1260 - (500 + 600) = -160hrs
• During June:
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 0hrs
3- remaining units = 1000hrs
4- Required/downtime units = 1 - (2 + 3) = 1260 - 1000 = 260hrs
• During July:
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 0hrs
3- remaining units = 0hrs
4- Required/downtime units = 1 - (2 + 3) = 1260 - 0 = 1260hrs
Regarding that I tried to spreadsheet fields’ customized options but I think I chose a wrong options so If any one have any idea via resource usage spreadsheet or any other report/way please feed me back with steps.
Regards,
Abeer
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 500hrs
3- remaining units = 600
4- Required/downtime units = 1 - (2 + 3) = 1260 - (500 + 600) = -160hrs
• During June:
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 0hrs
3- remaining units = 1000hrs
4- Required/downtime units = 1 - (2 + 3) = 1260 - 1000 = 260hrs
• During July:
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 0hrs
3- remaining units = 0hrs
4- Required/downtime units = 1 - (2 + 3) = 1260 - 0 = 1260hrs
Regarding that I tried to spreadsheet fields’ customized options but I think I chose a wrong options so If any one have any idea via resource usage spreadsheet or any other report/way please feed me back with steps.
Regards,
Abeer
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?