Skip to content

P6; Resource Usage Spreadsheet

Abeer MahmoudMember for 18 years 3 months
Created
2
4
0
• During May:
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 500hrs
3- remaining units = 600
4- Required/downtime units = 1 - (2 + 3) = 1260 - (500 + 600) = -160hrs

• During June:
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 0hrs
3- remaining units = 1000hrs
4- Required/downtime units = 1 - (2 + 3) = 1260 - 1000 = 260hrs

• During July:
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 0hrs
3- remaining units = 0hrs
4- Required/downtime units = 1 - (2 + 3) = 1260 - 0 = 1260hrs

Regarding that I tried to spreadsheet fields’ customized options but I think I chose a wrong options so If any one have any idea via resource usage spreadsheet or any other report/way please feed me back with steps.

Regards,

Abeer

2 replies

Oldest first
  1. 0
    Abeer Mahmoud ·
    Dear All,

    At P6, Kindly note that if I have a resource code R#1 limit is 42hrs per day this resource was assigned for many activities starting in Mar. and finished in Aug.

    And I updated schedule in May 10, 2009

    So I need a resource usage spreadsheet showing the following data:
    • During May:
    1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
    2- actual units = 500hrs
    3- remaining units = 600
    4- Required/downtime units = 1 - (2 + 3) = 1260 - (500 + 600) = -160hrs

    • During June:
    1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
    2- actual units = 0hrs
    3- remaining units = 1000hrs
    4- Required/downtime units = 1 - (2 + 3) = 1260 - 1000 = 260hrs

    • During July:
    1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
    2- actual units = 0hrs
    3- remaining units = 0hrs
    4- Required/downtime units = 1 - (2 + 3) = 1260 - 0 = 1260hrs

    Regarding that I tried to spreadsheet fields’ customized options but I think I chose a wrong options so If any one have any idea via resource usage spreadsheet or any other report/way please feed me back with steps.


    Regards,

    Abeer
  2. 0
    Mike Testro ·
    Hi Abeer

    I have moved this thread to the p6 forum - you will get a better response here.

    Best regards

    Mike Testro

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?