What is the simplest and easiet way to allocate resource and cost at a time for an activity in P6?


Thanks

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi John,

    Simplest way is to select all necessary activities that required to allocate resource and select the "Assign Resources" located at the right corner of your screen.

    The other way around is to export to excel.

    Regards.

    Arnold