Constraints Activity Hide

Shahzad AhmadMember for 18 years 8 months
Created
1
4
0
Hi All

I had imported a P3 Schedule in to P6

afetr imported Constraints activity are missing /hidden.

I am wondering where are they gone?

can anyone advise me how to recall them.


Thanks
Shahzad

1 reply

Oldest first
  1. 0
    Valerii Buturlakin ·
    Shahzad

    Check your import options and check if the any filters are turn on.

    Best regards

    Valerii