Question about late dates

Brian YungMember for 17 years 7 months
Created
1
1
0
Good day Gentlemen,

I would like to know why P6 show late dates eventhough the activity is comlete. From memory, in P3 whenever an activity is completes, the late start/finish date would either be empty or show the actual dates.

Is this normal?

Regards,

Brian

1 reply

Oldest first
  1. 0
    Dieter Wambach ·
    Brian

    Yes, it’s by design. If an activity has an actual finish, the algorithm doesn’t touch it and leaves the late finish. You can use it to compare with original planning. The field "Finish" turns from early to actual finish.

    Regards
    Dieter