P6 - resource early start vs activity early start

Phil MontgomeryMember for 19 years 7 months
Created
3
3
0
Is there a way to include resource early start date in the activity layout view (rather than activity early start)?

3 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Phil

    Therefore you have the view "Assignments" - "Start" vs "Activity Start".

    Regards
    Dieter
  2. 0
    Phil Montgomery ·
    I publish Activity layouts in HTM format because the grouping, sorting, and filterig is more user friendly across multiple projects. I do not want to publish from assignments layouts becasue Grouping, sorting, and filtering is not as robust. I want to publish a layout that contains data elements from both activity and assignment view. Specifically, i want to include resource "remaining early start" in an activity layout, that i will publish as an HTM file. I suspect no one is running a true ’resource dependent’ schedule?
  3. 0
    Dieter Wambach ·
    Phil

    Resource Early Start may be different for each assignment. From Activity point of view it’s a list. Which one to be used?

    I don’t know how group&sort and filtering isn’t robust for the assignment view.

    That you are running a true ’resource dependent’ might be one more reason to have a closer look at this view.

    Regards
    Dieter