Out of Sequence Report

James BraghiniMember for 18 years 5 months
Created
3
2
0
Has anyone created or knows where to find this report in P6?

3 replies

Oldest first
  1. 0
    Rafael Davila ·
    It is part of the updating report P6 generate after running a regular schedule update.
    I dont have P6 but have seen it there.
  2. 0
    Douglas Byles ·
    Hi James,
    You will find this information in the Schedule Log which is created when you schedule the project.

    Just click the button to schedule (or press F9) and you will see the View Log button. Of course the Log wont exist if you haven’t scheduled with the "Log To File" check box selected.

    Regards,
    Doug
  3. 0
    James Braghini ·
    Thanks, this works perfect. Have a great day.

    James B.