Hi All,

Can anyone tell me or guide me on how do i customize reports using Modify Report feature of P5 or P6. it goes to some kinda ruler based thing and is not very easy to use as far as i had a look. The report wizard lets you create reports but everything that i want cannot be complied into one report with the wizard. The help file says that i need to use the report editor in order to get all the information as per my desired look by using the Report Modify or Report editor tool. Please can anyone help me with this. If anyone has some document/manual or any other notes can you please share that with me.

Please help me.

Thanks and Regards,

Manik

13 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Manik
    If you’ll have a look into the "PMRefMan.pdf" --> Customizing Projects --> Customizing Reports --> Using the Report Editor.
    This probably will be the best introduction. the best way will be then to learn it by yourself.
    Some hints:
    Allways work with a copy.
    If you’ll need an additional data item to the wizzard, add another item with the wizzards, to replace it with the editor.
    Time distributed data: Allways create the table with the wizzard, no chance to do it with the editor.
    Use the preview button.
    There is an exit "Cancel".
    Good luck!
    Dieter
  2. 0
    Manik Nath ·
    Hi Dieter,

    So many thanks for your help but where do i find this PMREFMAN.pdf


    Warm Regards and Best Wishes,
  3. 0
    Dieter Wambach ·
    Hi Manik
    The third cd out of the set delivered by Primavera is the documentation cd. There you can find this and other helpful files.
    Regards
    Dieter
  4. 0
    Manik Nath ·
    Hi Dieter,

    I don’t have the CD as i am using P6 in my company and the software is loaded at our server in USA and all the project controllers across the globe use it via CITRIX imaging server. So no one will be having the CD of documentation of P6 and that is the problem. Can you provide me with the document you are talking about or the part which will help me. Or any website where i can get that.

    Regards,

    Manik
  5. 0
    Dieter Wambach ·
    Hi Manik
    If You’ll send me your Mail address, I’ll send it. Even zipped, the mail will have >7MB. Check first if you can receive that size.
    Regards
    Dieter
  6. 0
    Dieter Wambach ·
    Hi Mainik
    One remark: Your IT people should put some of the documentation files onto the server.
    Dieter
  7. 0
    Manik Nath ·
    Hi Dieter,

    Thanks a lot for your help.
    You can send the files to manik_nath@yahoo.com and copy them to maniknath@gmail.com

    About your comment we have already asked them to do so and the IT guys will come up with something which will help us. But it may take sometime as they are already working on something with the P6 database.

    Regards,

    Manik
  8. 0
    Dieter Wambach ·
    It’s done
    Dieter
  9. 0
    Manik Nath ·
    Hi Dieter,

    I haven’t received it yet :-(


    regards,

    Manik
  10. 0
    Dieter Wambach ·
    Hi Manik
    Just a little patience. Until now I didn’t receive an error message. I sent it to both adresses.
    Dieter
  11. 0
    Manik Nath ·
    Hi Dieter,

    So many thanks mate. I have receive dthe file. I am so very thankful to you for helping me.

    Many Thanks.

    Regards,

    Manik
  12. 0
    Dieter Wambach ·
    It was a pleasure
    Dieter
  13. 0
    Pratishtha Chauhan ·

    hi manik,can u please share

    hi manik,

    can u please share the manual with me.
    i am a project scheduler, and i need to customize my report using p6 urgently.

     

    please help as it will be greatly appreciated.

     

    thanks and regards,

    PRATISHTHA

    PLANNING AND INTERIORS

     

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?