Cost
In the Open Standard
Rohit RangnekarMember for 17 years 4 months
- Created
- 1
- 2
0
Dear All,
When I am assigning a material whose unit of measure is each to an activity “A” whose duration is 2days , result it shows is like remaining units / time = 16ea/d and price/unit = 1000/ea.Total cost of this activity is not coming correct. Actually I want qty of 2nos material for this activity. So where does the need of remaining units / time has arose ? Total cost should be calculated as 2* 1000 = Rs. 2000 then why these hours and and units are coming in to play ?
Regards,
When I am assigning a material whose unit of measure is each to an activity “A” whose duration is 2days , result it shows is like remaining units / time = 16ea/d and price/unit = 1000/ea.Total cost of this activity is not coming correct. Actually I want qty of 2nos material for this activity. So where does the need of remaining units / time has arose ? Total cost should be calculated as 2* 1000 = Rs. 2000 then why these hours and and units are coming in to play ?
Regards,
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?