Dear All,


When I am assigning a material whose unit of measure is each to an activity “A” whose duration is 2days , result it shows is like remaining units / time = 16ea/d and price/unit = 1000/ea.Total cost of this activity is not coming correct. Actually I want qty of 2nos material for this activity. So where does the need of remaining units / time has arose ? Total cost should be calculated as 2* 1000 = Rs. 2000 then why these hours and and units are coming in to play ?


Regards,

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi Rohit,

    Try to change your Budgeted units into 2.

    Regards,

    Arnold