Skip to content

autocost for expenses in p5

Faik UlkuMember for 17 years 6 months
Created
6
1
0
although i click all autocost tools in all mennues including for expenses, p5 does not calculate automatically the percenteges and quantities of expenses according to activity percentages completions. who can tell me how to do that.

thanks in advance.

6 replies

Oldest first
  1. 0
    Khuong Do ·
    Hi.
    You might need to choose the "Accrual type" of Expense to "Uniform over Activity".
  2. 0
    Faik Ulku ·
    i already did it but it doesnt work. strange. may be it is impossible for expenses
  3. 0
    Mark Porter ·
    Hi Faik,

    If the auto compute acutals option is selected in the check box, the actual/remaining cost are automatically updated when project actuals are applied via the => ’Tools’ => ’Apply Actuals’ menu. This assumes that the expenses have been accured according to plan.

    Note; If you also have any resources with the auto compute actuals check box selected, they will also be updated according to plan.

    Without actually doing it myself, If I were aiming to update the expense % complete, my personal recommendation would be to export the activity data’s activity % complete to an excel spreadsheet, and then also export the expenses to excel and then I would perform a "lookup" function to apply the activity % complete to the expense % complete.

    Hope that this helps

    Kind Regards

    Mark Porter
  4. 0
    Faik Ulku ·
    Hi Mark

    thank you very much, as i remember i attemted also apply actuals menu but nothing changed. i ll try it again.

    regards
  5. 0
    Mark Porter ·
    Hi Faik,

    A couple of other quick things that you could possible consider are:

    1) You have the "Apply Actuals" privlege set as part of your project security profile,

    2) The project is checked in & active,

    3) You have resources assigned (that also have the auto-compute actuals checked) to the activities that you are planning on updating via the "Apply Actuals" function in the tools menu (I don’t think it works otherwise), alternatively, another option is to use the view => progress spotlight and then tools => Update Progress... to progress your activities. I haven’t actually done this so I will be very interested in your results
  6. 0
    David Kelly ·
    Does it help to know that expenses are "autocosted" according to the activity’s "planned" dates, not their "early" dates"

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?