Skip to content

Expenses Actual Cost Based on Activity Physical%

Troon SigmaMember for 6 years 6 months
Created
5
2
0

Hi,

 

I have added an expense to my activity.  Is it possible that the 'actual cost' of the expense change as physical % complete of the activity changes?

 

Thanks

5 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    a Global chnage will not work

    a Global chnage will not work here

    export the physcial % complete and the Expense % complete to excel

    thne copy the physcial % complete to the expense complete and then import back into p6

  2. 0
    Zoltan Palffy ·

    a Global chnage will not work

    a Global chnage will not work here

    export the physcial % complete and the Expense % complete to excel

    thne copy the physcial % complete to the expense complete and then import back into p6

  3. 0
    Troon Sigma ·

    Thanks a lot Zoltan

    Thanks a lot Zoltan

  4. 0
    Troon Sigma ·

    Thanks a lot Zoltan

    Thanks a lot Zoltan

  5. 0
    Zoltan Palffy ·

    glad I could help

    glad I could help 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?