CLIENT REVIEW
In the Open Standard
Shiv RaoMember for 18 years 7 months
- Created
- 2
- 1
0
Good day friends ,
I have recenetly joined as an planner for "ENGINEER".
I was a planner for contractors for 10 yrs now. And know the tricks we play with programms.
But now its time to catch those tricks your contractor plays with you.
I use my Contractors programme to review. which is my job.
And i do following analysis?
Variance analysis w.r.t to last month report.
Variance analysis w.r.t to Baseline.
Claim Digger.
I could do few more like.
Float analysis.[ But why should i ?]
and would like to know what other analysis can be done in the reviewing process? From you experienced planners / client programmers.
If some one has a white paper describing what is expected from a planner in the reviewing process, plz send me a copy.
I have recenetly joined as an planner for "ENGINEER".
I was a planner for contractors for 10 yrs now. And know the tricks we play with programms.
But now its time to catch those tricks your contractor plays with you.
I use my Contractors programme to review. which is my job.
And i do following analysis?
Variance analysis w.r.t to last month report.
Variance analysis w.r.t to Baseline.
Claim Digger.
I could do few more like.
Float analysis.[ But why should i ?]
and would like to know what other analysis can be done in the reviewing process? From you experienced planners / client programmers.
If some one has a white paper describing what is expected from a planner in the reviewing process, plz send me a copy.
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?