cost account

Rohit RangnekarMember for 17 years 4 months
Created
1
2
0
Dear Sir,

I have set up a cost account for a project and under it certain child cost accounts for activities. Now I want to know where is the use of these cost accounts in primavera or in which report we can see any type of analysis related to cost account? Why they are used?

Regards,

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi Rohit,

    Cost Account they enable you to track activity costs and earned value according to your organization’s specific cost account codes.

    The cost account is used for resource assignments to activities and project expenses.

    Regards,

    Arnold