Activity Inserting

Mustafa IsmayilzadaMember for 19 years 4 months
Created
2
17
0
Hi there,
Activity inserting in P6 goes by +10. How can I make it adding +1 while I am inserting new activity?

Unlike in P3 -> Options -> Activity Inserting.... I can’t find Options at all :)

Thanking you all again for your help

2 replies

Oldest first
  1. 0
    Ferdinand U. ·
    From Projects View

    Project Details

    Under Defaults Tab, Change the Auto Numbering Defaults Setting for Increment
  2. 0
    Mustafa Ismayilzada ·
    Thanks very much. It works.