Dear All,

what is the difference between schedule % complete , duration % complete and activity % complete ?

Regards,

2 replies

Oldest first
  1. 0
    Niles Luo ·
    hi,
    schedule % complete is calculated base on baseline and data date.
    duration % complete=(OD-RD)/OD
    activity % complete depends % Complete Type and it should be one of duration,units,physical.

    Regards
  2. 0
    Tyler Tan ·
    activity % complete can be choiced in the "general" tab of "activity".