Skip to content

Progress

Rohit RangnekarMember for 17 years 4 months
Created
5
1
0
Dear All,

I am trying my best for understanding topic “progress’ but still have lot of doubts. I am giving an example , pls. anybody explain :-

My activity is of 2days duration , starting on 15/6/09 and ending on 16/6/09 which means that at the end of 15/6/09 ,it should be completed as 50%. Now my questions are:-

a) what should I do to see my planned progress at the end of day 15/6/09?
b) Now I see planned progress as 50% , now I want to apply actuals on the date , what should/steps I should perform?
c) After performing the steps I want to put my activity actual percent completed as 40%, how can I do this? And after that I want to see that due to delay in my activity completion, how my schedule has effected , how can I see this ?
d) If I came to know that due to delay my schedule has gone up by 1day but I want inspite of delay to complete the project on time , what are the available options with me?

Thanx in advance. Answers to these will be very helpful to me. So pls. help.

Regards,

5 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Rohit

    Please tell us what software you are using.

    Also whether your durations are resource driven.

    Best regards

    Mike Testro
  2. 0
    Rohit Rangnekar ·
    P5 AND ARE ACTIVITY DEPENDENT.

    REGARDS,
  3. 0
    Mike Testro ·
    Hi Rohit

    I have moved this thread to P5 - P6 and deleted your duplicate thread.

    Please do not use duplicate threads in future.

    Also I did not understand your answer that the durationds were "activity dependant".

    Best regards

    Mike Testro
  4. 0
    Rohit Rangnekar ·
    SORRY,

    MY DURATION IS RESOURCE DRIVEN.
  5. 0
    A D ·
    Thats some basic stuff.

    If u have P6 Manual, then read from page 283 to page 315

    :-)

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?