WBS for building construction

Alaa Al hajMember for 18 years 11 months
Created
2
2
0


please i am working now on preparing a schedule for building construction from scratch to deliver the building to the client including finishing

i suggest the below WBS

1. sub structure
2. super structure

1.1 excavation
1.2 foundation


2.1 skeleton
2.2 finishing
2.3 landscape
2.4 services

please i need more clarification
links or books about construction building schedule - sequence

2 replies

Oldest first
  1. 0
    Rafael Davila ·
    Alaa,

    In our geographical area the construction industry have a standardized way of organizing data. We follow the CSI / Construction Specifications Institute, I don’t mean literally but at least within the major work divisions. We organize construction estimates, bid/proposal breakdown, payment breakdown, specifications, drawings and schedules using this standard. Everyone knows the standard major divisions. Remember it is a US Standard maybe you have a European Standard.

    http://www.constructionnotebook.com/ipin2/CSIDivisions.asp

    The major CSI divisions are:
    Division 1          General Requirements
    Division 2          Site Construction
    Division 3          Concrete
    Division 4          Masonry
    Division 5          Metals
    Division 6          Wood and Plastics
    Division 7          Thermal and Moisture Protection
    Division 8          Doors and Windows
    Division 9          Finishes
    Division 10          Specialties
    Division 11          Equipment
    Division 12          Furnishings
    Division 13          Special Construction
    Division 14          Conveying Systems
    Division 15          Mechanical
    Division 16          Electrical

    There is no a Universal WBS for scheduling and even the application of a related standard should be adapted to the particular needs, or at times specific contractual requirements. Usually for my type of works I use the top WBS level for Construction Phases, the next for Construction Areas and finally the CSI Divisions, for my schedules I keep General Conditions as a Construction area instead of a CSI Division. Within Divisions I do not strictly follow the CSI numbering. For small jobs at times I even skip the WBS level for Divisions and use a numbering sequence following the CSI Division Numbering.

    In summary my preferred WBS Structure is

    PROJECT. PHASE. AREA. CSI-DIVISION

    I hope someone joins and provide us with your standard, for scheduling the major titles should do it.

    Cordially,

    Rafael

    PS. As a matter of fact I usually mimic WBS within Primavera SureTrak using Activity Codes; I find this method of organizing easier and more flexible especially when your software does not provide for multiple WBS.

  2. 0
    Samer Zawaydeh ·
    Dear Ala’a

    Rafael gave you all the components of the project, now you have to include them in your schedule depending on your project design drawings and method statement.

    Each program of work should include the following Major sections:

    I. Material Submittals: Civil, Architectural, Mechanical and Electrical.
    II. Shop drawings Submittals; Civil, Architectural, Mechanical and Electrical.
    III. Procurement. A sub divison for LONG LEAD ITEMS>
    IV. Construction. This is what you mentioned in your email.
    V. Testing and Commissioning and Handing over.

    In the Construction section you will have the following.

    - Mobilization
    - Site Survey
    - Excavation
    - Footing
    - shuttering
    - Reinforcement
    - Concreting.
    - Vertical Elements
    - shuttering
    - Reinforcement
    - Concreting.
    - Tie Beams
    - shuttering
    - Reinforcement
    - Concreting.

    - Substruction insulation (if any)
    - Substruction insulation protection (if any)
    - Fill in layers
    - Slab on grade blinding
    - Slab on grade insulation
    - Slab on grade reinforcement
    - Slab on grade concreting.

    Super Structure.
    - Columns
    - shuttering
    - Reinforcement
    - Concreting.
    - Slabs
    - shuttering
    - Reinforcement
    - Concreting.
    - External Facade
    - Stone
    - Block
    - Aluminum
    - Finishes
    - Block Work
    - Plastering
    - Tiling
    - Paints
    Mechanical Works
    1st fix
    2nd fix
    3rd fix
    Electrical Works
    1st fix
    2nd fix
    3rd fix

    If you mention a brief description about your building, we can complete your activities in a short time.

    With kind regards,

    Samer