Resource Assignments
In the Open Standard
Clay WaldropMember for 17 years 4 months
- Created
- 2
- 4
0
Every month I have to paste my resource assignments from P6 to excel and I am running into a formatting issue.
My resources in P6 look like this:
1 - 10hrs
3 - 10hrs
5 - 10hrs
The template I have to paste into looks like this:
1
2
3
4
5
Is there a way that I can for P6 to show resources 2 & 4 even if they don’t have any value so that I’m not constantly adjusting my data to fit theirs?
My resources in P6 look like this:
1 - 10hrs
3 - 10hrs
5 - 10hrs
The template I have to paste into looks like this:
1
2
3
4
5
Is there a way that I can for P6 to show resources 2 & 4 even if they don’t have any value so that I’m not constantly adjusting my data to fit theirs?
2 replies
Oldest firstLog in or join to reply