Progress Resources

Alexandre Azevedo da CruzMember for 17 years 11 months
Created
1
1
0
Hi,

I’m trying to calculate the progress of resources on several tasks.
Each task as several resources, and each resource as a different progress.

Does anyone has an idea about how to input the % complete task for each resource independently, and have then a % complete task?

Thank you all for your answers.

Regards
Alexandre

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi Alexandre,

    Welcome to Planning Planet.

    Go to "Assignments" Group them by Resource Name and WBS or Codes then show the "Unit % Complete", "Actual Units" in the column depending on your requirements and manually input the actual units.

    If you need to know the % complete for each task then I would suggest to use the Physical % Complete.

    Regards,

    Arnold