Est weight

Jason LIMember for 18 years 9 months
Created
1
1
0
Dear all,
What’s the meaning of Est weight for WBS/activity, and how to correctly use it.
Your answer is appreciated.

1 reply

Oldest first
  1. 0
    Ronald Romero ·
    Jack,

    My understanding for the Est. Weight is for top-down estimation. Breaking down the project by WBS then using a experience or mathematical function that is related to the productivivity of the organization to give weight for each WBS levels.

    I try to use this P6 feature and give you more feedback on this planning parameter.

    Ronnie