Activity completion
In the Open Standard
Rohit RangnekarMember for 17 years 4 months
- Created
- 1
- 2
0
My activity is starting from 4.6.09 and ending on 16.6.09 . But due to certain circumstances , it got only 80% completed on the finishing day due to which its actual completion appended to 18.6.09. Since the activity was critical , what steps we could have taken to complete the activity on time knowing that activity is going to be delayed?.
Regards
Regards
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?