apply actuals

Jason LIMember for 18 years 9 months
Created
4
1
0
Dear all:
Have you ever use the function "apply acutal" at menu tools, what’s the meaning of "apply actuals", and how to use it correctly.
Thanks

4 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Jack,

    Used to update or apply actual to your activities and update the current data date.

    For more details try to check the Help Menu.

    Regards,

    Arnold

  2. 0
    Jason LI ·
    Thanks Arnold,
    I viewed the help, but still now understand the difference between apply actual and schedule. how to use this two method accordingly.
  3. 0
    Duy Pham ·
    Hi Jack,

    In Primavera Manual, Apply Actual has been defined:


    (Once progress is recorded by approving timesheets, entering actual data, and/or setting Auto Compute Actuals options, you must apply actuals. Applying actuals schedules activities with progress and/or that have the Auto Compute Actuals option set. When you apply actuals, you move the data date or “time now.” The module schedules activities only within the specified timescale (between the current data date and new data date) and calculates progress for those activities that are set to automatically calculate actuals.)


    Hope it helps.

    Regards
  4. 0
    Jason LI ·
    Tanks Duy.
    I never use timesheet. so it’s ok for me.