Primavera’s Cand Reporting tool show baseline data
In the Open Standard
Kris HermanMember for 17 years 3 months
- Created
- 1
- 2
0
How do you create a single report with Primavera’s own reporting tool to show the per resource baseline hrs vs. the actual hrs? It is so hard trying to use what comes with Primavera. I can show the budgeted hrs or show the per role BL hrs but nothing else.
I know I could look at Oracle-Discovery to generate this required report, but hope someone out there can help me.
Thank you for your reply
Kris