Primavera’s Cand Reporting tool show baseline data

Kris HermanMember for 17 years 4 months
Created
1
17
0

How do you create a single report with Primavera’s own reporting tool to show the per resource baseline hrs vs. the actual hrs? It is so hard trying to use what comes with Primavera. I can show the budgeted hrs or show the per role BL hrs but nothing else.

I know I could look at Oracle-Discovery to generate this required report, but hope someone out there can help me.

Thank you for your reply

Kris

1 reply

Oldest first
  1. 0
    Khuong Do ·
    Hi.
    When create a new report, you can choose to show many column which start with BL Project or BL 1... We can show most of data of the baseline.
    What kind of field you need to show ?

Log in or join to reply