SAP Primavera integration

Nasreen AlmutawaMember for 17 years 7 months
Created
6
5
0
Is it easy to convert data from primavera to SAP as a project done internally ( Inside the company) or should i not bother and seek an outside party who could install a special software to do this ?

and if so which companies do it ?

6 replies

Oldest first
  1. 0
    Shahzad Ahmad ·
    Hi

    You could ask to your SAP administrator to do so....

    one of my friend try to do it but he faild....due to SAP administrator restriction...

    REG.
    Shahzad
  2. 0
    M. Kamel Bessekri ·
    Hi
    As long as I know, an intermediate a software is used to convert the data from primavera .
    via an integration Interface . In my company this is called MAAP .
    Then can the data be treated by SAP

    Regards

    Kamel
  3. 0
    James Shimmon ·
    Nasreen
    What type of data do you wish to be transferred?
    We run Primavera with SAP via a Citrix interface so may be able to help.
    Cheers

    Shimmo
  4. 0
    Ian Thomson ·
    We use a product called i-connect which can be configured to transfer data to/from SAP including updating sap once the plan has been updated. this is a very versatile tool which allows various modes of transfer (one SAP operation to 1 activity, all operations rolled up to 1 activity with multiple resources, all disciplines rolled up to a seperate activity per discipline) i-connect can also transfer across future SAP plans (planned but not currently scheduled to a work order) as a customisation.

    see attached link for some basic info
    (http://www.monitor-mpower.com/software/iconnect.php?pageid=92)

    i have not seen many other tools that convert data from SAP to primavera but i assume this one is one of the market leaders.

    if you need anyh more help just ask

    ian
  5. 0
    Arthur Godbeer ·
    Primavera has its own SAP integration product, Primavera Inspire. It is the only such product that has SAP EBS (Endorsed Business Solution) certification.
  6. 0
    Santosh Bhat ·

    Or look into another

    Or look into another Scheduling system that works with SAP like Safran Project.