Earned Value S Curve, Early vs. Late

Jose Valdez MarcosMember for 25 years 5 months
Created
10
3
0
Hi all,

I have prepared a WBS earned value report based on all my activity % weighting (Project->WBS). This is working well. Now our client requires an S-Curve between early and late dates. In P3, this is possible, I don’t know in P6. Is there an equivalent resource curve in P6 where I can show these 2 curves (early vs. late dates)?

Regards,

Joe

10 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Jose,

    This is possible. Make two copies of your baseline schedule. Then assign it into your current schedule. If you need the steps, forward to me your email.

    Regards,

    Arnold
  2. 0
    Scarllet Pimpernel ·
    Dear Arnold,

    Please send me:

    ellenedar@yahoo.com

    Many thanks

    Scarllet
  3. 0
    Jose Valdez Marcos ·
    Hi Arnold,

    Please send me to my email address:

    jose.marcos@macdow.com.au

    Thanks in advance,

    Joe
  4. 0
    Arnold Puy ·
    Hi Jose,

    Already sent.

  5. 0
    Scarllet Pimpernel ·
    Dear Arnold,

    This is to acknowledge I receive the file.

    More power to you.

    Many thanks,
    Scarlett
  6. 0
    Shafeeque . ·
    Dear Arnold,

    Pls send me too..
    shfqp@yahoo.com

    Thanks,
    Shah
  7. 0
    Jose Valdez Marcos ·
    Hi Arnold,

    I already received your email with attachment.

    Many thanks,

    Joe
  8. 0
    Rex Lorenzo ·
    Dear all,

    A late earned value of progressing program.... Is it useful to use when some of the activies had a negative total float?

    As far as project that I involved with we usually use an early and late curve in planning stage wherein the lowest total float is zero. Wish to enhance my knowledge if you could share me how you extract a late data with activities having a negative total float.

    Regards,
    RL
  9. 0
    vinay M ·

    Joe, can you please send me

    Joe,

    can you please send me the copy of your S curve prepared on WBS earned value report based on  activity % weighting (Project->WBS) two curves (early vs. late dates)

     

    Thanks & regards

    V

    viny22@yahoo.com

  10. 0
    Haris Famil Parol ·

    Dear Arnold

    i am making S cruves for Early and Late loading values extracted from P3.1 and P6 to Excel. If u know the method to generate curve within the P6 with 2 baselines, i would like to know too.

    Please send me your steps to harisfamil@gmail.com

    Thanks in advance

    Regards

     

    Haris