Dates in P6
In the Open Standard
Scarllet PimpernelMember for 17 years 3 months
- Created
- 4
- 1
0
Dear All,
I have this data in P6:
Start Date: 29-Sep-08
Finish Date: 20-Feb-11
Actual Start: 29-Sep-09
Actual Finish:
Early Start: 26-Jun-09
Early Finish: 20-Feb-11
Late Start: 30-Sep-08
Late Finish: 02-Apr-12
Total Float = 324
Data Date: 26-June-09
Strange! Why is the early start 26-Ju-09 when the activity started already? Why is the late start 30-Sep-08 when the total float is only 324?
Please let me know the reason whoever notice the same.
Many thanks,
Scarlett
I have this data in P6:
Start Date: 29-Sep-08
Finish Date: 20-Feb-11
Actual Start: 29-Sep-09
Actual Finish:
Early Start: 26-Jun-09
Early Finish: 20-Feb-11
Late Start: 30-Sep-08
Late Finish: 02-Apr-12
Total Float = 324
Data Date: 26-June-09
Strange! Why is the early start 26-Ju-09 when the activity started already? Why is the late start 30-Sep-08 when the total float is only 324?
Please let me know the reason whoever notice the same.
Many thanks,
Scarlett
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?