Resource Assignment Dates not equal to Activity Dates
In the Open Standard
Peter BennettsMember for 16 years 5 months
- Created
- 10
- 8
0
I am experiencing consistent problems with the dates on the Resources assigned to an Activity being at variance to the dates of that activity despite them being originally aligned.
Does anyone know the mechanism, settings or steps that may been taken that will cause these dates to become misligned, the images below from the Assigments View illustrates the problem.
10 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?