Unit/Time Format

Edniel RecamadasMember for 17 years 5 months
Created
1
2
0
Dear All,

Does the unit/time format fixed in hours/day? Or it can be change to i.e. mandays/day, etc.

Urgent help pls.

Thanks

1 reply

Oldest first
  1. 0
    R. Catalan ·
    Edniel,

    Ideally, unit/time format should be in man-hours/day. But you can change the format settings.

    Go to:
    1) Admin Preferences - to change the hours per time period
    2) Then Edit/User Preferences to change the settings for the unit/time format.

    P6 Manual >> "Primavera calculates and stores time unit values in hourly increments. When you display or enter data in time unit fields in increements other than hours, the PM module converts the data based on the hours per time period settings."

    Regards,
    R. Catalan