What am I missing here?
In the Open Standard
Gary WhiteheadMember for 17 years 6 months
- Created
- 4
- 3
0
I’m clearly being stupid here, but i can’t work out how. Please help!
I create a new (task dependant) activity (fixed duration & units), with no relationships, no resources and no constraints.
I assign it a 7-day calendar with no exceptions, no non-work days, and 8hrs a day standard working time.
Activity start date = project start date = 14th Sep 09
Below are the finish dates P6 gives me for varying original durations:
0 days: 14th Sep
1d: 15th Sep
2d: 16th Sep
3d: 17th Sep
4d: 18th Sep
5d: 20th Sep
6d: 21st Sep
7d: 22nd Sep
8d: 23rd Sep
9d: 25th Sep
10d: 26th Sep
11d: 27th Sep
12d: 28th Sep
13d: 30th Sep
What is happening on the bolded dates? why doesn’t 5d duration give me a 19th Sep finish?
Thanks in advance,
G
I create a new (task dependant) activity (fixed duration & units), with no relationships, no resources and no constraints.
I assign it a 7-day calendar with no exceptions, no non-work days, and 8hrs a day standard working time.
Activity start date = project start date = 14th Sep 09
Below are the finish dates P6 gives me for varying original durations:
0 days: 14th Sep
1d: 15th Sep
2d: 16th Sep
3d: 17th Sep
4d: 18th Sep
5d: 20th Sep
6d: 21st Sep
7d: 22nd Sep
8d: 23rd Sep
9d: 25th Sep
10d: 26th Sep
11d: 27th Sep
12d: 28th Sep
13d: 30th Sep
What is happening on the bolded dates? why doesn’t 5d duration give me a 19th Sep finish?
Thanks in advance,
G
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?