Primavera Baseline - Even Without It, Data is There, howcome?
- Created
- 10
- 5
Hi,
I understand purpose of having baseline - it is used for comparing actual data with original data.
However, I tried this and found out that Primavera maintains baseline data even if we did not create it.
1. I make a plan.
2. I enter actual progress.
3. Now, I open columns like - BL Project Duration, BL Project Start, BL Project Finish - These are the baseline columns and these columns are showing original plan data even I did not create baseline. Even the original data is showing in the gantt chart in baseline bars correctly. Howcome? It implies we don't really need to manually create any baseline.
Can Zoltan or anyone else expert there explain this please.
I have attached a screenshot as well to confirm what I said
10 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?