Dears,
In P6 we have done the recovery with cost loaded to expenses category. However the remaining cost shows same as original budgeted cost. ie actual cost or earned value is not deductted.
How I can correct this?

2 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Ajith,

    You need to update your Actual & Earned Value Cost based on the % complete or work done.

    Likewise, make sure that in Project Setting under Calculation, mark the check box next to "Subtract Actual from At Completion".

    Regards,

    Arnold
  2. 0
    Ferdinand Fincalero, PMP ·
    Ajith,

    Try checking out your calculation settings. Go to projects, calculation tab, then tick on "recalculate actual..." and "link actual..."

    Hope it will do.