Cost Loading in Programme

Edniel RecamadasMember for 17 years 5 months
Created
3
2
0
Dear All,

I hope it’s not too much for to ask help again. I really appreciate the assistance of Ferdinand & Dieter on my other recent tread.

This time, I want to know which is the best way to cost load a programme, is it by using the expenses category or creating a resource (cost) thru a nonlabor cost parameter?

I’m talking about the easiest way and tracking it thru Earned Value system.

Hope to get more feedbacks.

Regards,
Edniel

3 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Dear Edniel

    It depends on your costs and of your needs for controlling. I assume you’ll need both:

    - Costs related to a resource (men, equipment, material) and time: Resource, rate per unit, and units or budget for an assignment (parameter "rate source")
    - Costs related to an activity, e.g. a milestone --> expenses

    Regards
    Dieter
  2. 0
    Mertz Balanon ·

    HI All!, Regarding the above

    HI All!,

    Regarding the above question I would like to ask also because I have cost loaded my activity and put it as a resources cost, but when i start to up date the budget cost become Zero.. where can i put my cost of a certain acivity and also how can i show it in Tabular cost loading so i can derive it for muy cash flow?..

     

    Thanks help will be very much appreciated!

  3. 0
    Aries Arian ·

    Hi Edniel,You can upload cost

    Hi Edniel,

    You can upload cost in both ways.It depends on the requirement of your organization.I have worked with an organization in the start of my career and i was only required to provide the schedule and actual % complete.Resource loading was not their requirement.For that I just entered the activity cost against all activities and perform Earned value analysis using that limited data.But when their is requirement of Resource assignment and Histrograms,then obviously you make a complete schedule loaded with resources and expenses in all respects.So if you just need to enter the activity cost from BOQ, you can use expence tab for your ease.

    Regards

Log in or join to reply