Importing Projects from P3.1 to P6

Abdul KhadeerMember for 22 years 1 month
Created
1
4
0
Dear all,

I have P6 Installed on my PC and i have schedule from contractor (prx file). i do not have P3.1 installed on my PC. Can i import this prx file to P6.

your help will be appreciated.

1 reply

Oldest first
  1. 0
    Khuong Do ·
    Hi.
    You can change extension of the file from prx to exe. Then double click to unzip the file to around 20 file in P3 format.
    And you can import to P6 now.