Skip to content

Progress Report

Ruel CamaquinMember for 17 years 11 months
Created
1
1
0
Dear All,

Just like to know how can i add "To Date % Complete", "Previous % Complete", "This Period % Complete" and "Balance % to Complete" Columns in a project schedule, so it can also serve as my weekly progress report. I did it once in p3 but we now migrated to p6 (and my formal training is in p3).

Thanks in advance & cheers!

Ruel

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi Ruel,

    You need to add User Defined Fields (UDF) and assign them. Then run the Global Change.

    Regards,

    Arnold

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?