Skip to content

Upgrading from P6 version 6.0 to 6.2.1

Richu RoseMember for 19 years 8 months
Created
3
3
0
Dear friends,

I have P6 version 6.0, is it possible to upgrade to version 6.2.1 without paying any money.

I have been to oracle’s website http://edelivery.oracle.com/EPD/Download/get_form
Is it possible to down load the file "Primavera P6 Client Applications v6.2.1" and install the file.

Regards,

Richu

3 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Richu

    This upgrade will be in steps: 6.0 --> 6.1 --> 6.2 --> 6.2.1

    The database must be upgraded as well. Maybe there is a skript to skip some of those steps. Study the text file on your installation-dvd - or in your downloaded files. There is a setup.exe

    You’ll receive a dvd from your local dealer, if you have a maintenance contract.

    Regards

    Dieter
  2. 0
    A D ·
    Hi Richu,

    U can also download upgrades from primavera / oracle website, if u dont have maintenance contract.

    But, as Dieter has said, install all updates in sequence. Dont jump directly to 6.2.1

  3. 0
    Richu Rose ·
    Dieter & Ravei,

    Thank you for the information.

    Regards,

    Richu

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?