Problem in updating Progress for Unit %
In the Open Standard
Anujkumar MishraMember for 18 years 1 month
- Created
- 1
- 3
0
Dear all,
I have created a project and assigned labor units as resource.
Duration type of the project is Fixed Duration and units
While updating the progress I have selected unit% for progress updating (as we can see the summarized progress at Level-1 on Unit % complete only).
Now, during updating I have observed that actual unit gets updated only first time of update.
e.g: Suppose activity A is having 200 Labor units. During first update of Unit% I have updated the progress as 50% then actual units are coming 100 but when I am again updating the progress to 60% actual units remains unchanged while Remaining and At completion units are changing. This leads to incorrect overall progress calculation (At Level-1).
Kindly help me and suggest solution.
I have created a project and assigned labor units as resource.
Duration type of the project is Fixed Duration and units
While updating the progress I have selected unit% for progress updating (as we can see the summarized progress at Level-1 on Unit % complete only).
Now, during updating I have observed that actual unit gets updated only first time of update.
e.g: Suppose activity A is having 200 Labor units. During first update of Unit% I have updated the progress as 50% then actual units are coming 100 but when I am again updating the progress to 60% actual units remains unchanged while Remaining and At completion units are changing. This leads to incorrect overall progress calculation (At Level-1).
Kindly help me and suggest solution.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?