Dear All,

After updating the percentage complete in P3 we uncheck the autocost tab and then schedule.Is there any option in p6 so that my percentage complete doesnot get changed.


Regards,

Anbin

5 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Anbin,

    There are two options you can apply.

    1. Use Physical % complete.
    2. Untick "Recalculate Actual Units and Cost when duration % complete changes".

    Regards,

    Arnold
  2. 0
    Anbin Ponnith ·
    Thanks a lot.,


    Regards,

    Anbin Ponnith
  3. 0
    Le Tuan ·
    Dear Arnold.
    Would you please to show me where untick of No.2 ? I cannot find it.
    Thanks
  4. 0
    Arnold Puy ·
    Hi Le,

    Go to Enterprise --> Projects --> Highlight your current open project --> Project Details, Calculations Tab, Resource Assignments..

    Hope this helps.

    Regards,

    Arnold
  5. 0
    Shahajahan Azeez ·

    Dear All,After Updating the

    Dear All,

    After Updating the Program in P6,we have number of -ve floats, how to check the certain value of -ve Float    (For example  -33d Float) ???  

    Regards

    Shahajahan