Can anyone tell me what is the main advantage of using P6 compared to P3??

What is methodology management in P6 ??


tHANKS

2 replies

Oldest first
  1. 0
    Ronald Winter ·
    Thusha,

    In my opinion, P3 is easier to install and use. It also has better graphics. P6 has way more features and handles complicated multi-schedule situations better and supports more simultaneous users.

    The biggest difference is that P3 is no longer for sale while P6 is sold world-wide. Good luck!
  2. 0
    D Artagnan ·
    I am just migrating from P3 to P6 and the latter is really more robust to handle complicated tasks. One thing that I really find interesting is that P6 runs faster than P3 when handling thousands of activities.