Skip to content

why the percent complete changes after scheduling

Anbin PonnithMember for 17 years 4 months
Created
1
2
0
Dear All,

After I enter the percentage complete for all activities and schedule,The percentage complete changes from what I have Entered.Also there are decimals seen in it.

Why its happening in P6.Do I have to change any settings.


With Thanks & Regards,

Anbin Ponnith

1 reply

Oldest first
  1. 0
    Dieter Wambach ·
    Anbin

    Have a look at the %-complete type:
    - Physical: entered manually
    - Duration or Units: calculated based on actual and remaining duration or units

    Switch off "Auto Compute Actuals"

    Regards

    Dieter

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?