P6 Decimal setting for manhours loading

Izam ZakariaMember for 20 years 4 months
Created
3
2
0
As reference made above, where I can find it?

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Izam,

    Go to --> Edit --> User Preferences --> Time Units tab, Units Format, Decimals, then change 0 to 1 or 2.

    Regards,

    Arnold
  2. 0
    Izam Zakaria ·
    u always there buddy ... thanks
  3. 0
    Arnold Puy ·

    You are welcome.

Log in or join to reply