Early Finish and Late Finish not matching and total float has negative decimal float
- Created
- 9
- 6
Situation:
I have attached below a snap shot of the first page of a baseline schedule submitted by a contractor. A Quick glance while reviewing the schedule shows that they have used a calender having different working hours during various months based on Ramdan reduced work hours etc. The default calender assigned in the project level is the same.
A must finish by constraint is assigned on 31-Aug-14 at project level.
One of the activity as seen in this picture "Mobilization Works" has been given an original duration of 14.50 days.
There are milestones with invalid relationships as per scheduling report; probably due to assigning FS predecessor relationship to a Finish Milestone etc.
Questions:
Are there any reasons other than the above for having a project late finish date earlier than the project early finish date, ,having fractions in total float?
Is it required to impose a must finish by constraint before starting the update process?
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?