"Your system is out of memory" for cost histogram.
In the Open Standard
Alex JanecekMember for 17 years 2 months
- Created
- 4
- 27
0
Hi, I am new to scheduling and new to this forum.
I am working on a schedule for a freeway project in Southern California and I am running into a very frustrating problem that Oracle P6 support has been no help with.
My problem is that when I try to generate a histogram for my cost resource, P6 uses up the Windows max memory for an application (2GB) and P6 locks up just before the histogram is created.
I can generate manhour resource histograms with no problems at all.
I am running P6 v6.2.1 with a brand new computer with 4GB RAM.
The problem resource is nonlabor and is assigned to 4600 activities for a total of about $372M.
Has anyone run into this problem or have any ideas on how to fix this?
I am working on a schedule for a freeway project in Southern California and I am running into a very frustrating problem that Oracle P6 support has been no help with.
My problem is that when I try to generate a histogram for my cost resource, P6 uses up the Windows max memory for an application (2GB) and P6 locks up just before the histogram is created.
I can generate manhour resource histograms with no problems at all.
I am running P6 v6.2.1 with a brand new computer with 4GB RAM.
The problem resource is nonlabor and is assigned to 4600 activities for a total of about $372M.
Has anyone run into this problem or have any ideas on how to fix this?
4 replies
Oldest firstLog in or join to reply