Problem With schedule Percent Complete

Amir ArjmandiMember for 19 years 5 months
Created
1
2
0
Hi
I have a problem with Schedule Percent complete.I can not get summarize percent In activity views, the P3E 5.0 or 6.0 doesn’t summarize schedule percent complete in WBS level and i can see it in activities level. also if i import a project from P3, software summarizes and shows it,automaticaly.
Thanks for your time.
Bye

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi Amir,

    Schedule % Complete does not roll up in summary band if:

    1. The Resource’s Price/Unit equal to Zero (0).

    2. If you assign Baseline to your project, make sure that all resource assignments you’ve made is the same as that with the current especially "Cost".

    3. Make sure that Budgeted Cost for both current & baseline schedule is greater than Zero (0).


    Regards,

    Arnold