Problem With schedule Percent Complete
In the Open Standard
Amir ArjmandiMember for 19 years 5 months
- Created
- 1
- 2
0
Hi
I have a problem with Schedule Percent complete.I can not get summarize percent In activity views, the P3E 5.0 or 6.0 doesn’t summarize schedule percent complete in WBS level and i can see it in activities level. also if i import a project from P3, software summarizes and shows it,automaticaly.
Thanks for your time.
Bye
I have a problem with Schedule Percent complete.I can not get summarize percent In activity views, the P3E 5.0 or 6.0 doesn’t summarize schedule percent complete in WBS level and i can see it in activities level. also if i import a project from P3, software summarizes and shows it,automaticaly.
Thanks for your time.
Bye
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?