Bearing Negative Total Float if Apply Must Finish date

Cecil SolivaMember for 22 years 6 months
Created
3
2
0
Hi Planners:

I made a project having an early finish date of October 15, 2010 and the same I provided to the project details must be finished on October 15, 2010. I found out that the Total Float of the critical Path changes from 0 to -1. How does P6 reads with this regards?


Thank you,

Cecil

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Cecil,

    Try to check the finish date.

    1. Go to Edit --> User Preferences --> Dates tab, Time, tick Show minutes and select the 12 hour (1:30 PM).
    2. Go to Enterprise --> Projects
    2. In Projects Detail Tab --> Dates
    3. In "Must Finish Date" if you notice the the time is 12:00 AM, change this to 4:00PM or 5:00PM. It depends on the calendar and time you use.

    Otherwise, check your finish date. It should be the same with "Must Finish Date especially the time.

    Regards,

    Arnold
  2. 0
    Cecil Soliva ·

    Thanks again Arnold..I’ve wasted a lot of time, thinking how it became -1 TF..


    regards,

    Cecil

  3. 0
    Arnold Puy ·

    You are welcome.