Total Original Duration!

Jonald CalaycayMember for 18 years 1 month
Created
3
2
0
Guys,

Greetings! i have imported a project from p3.1 to p6. most of what i imported is ok. my concern is that the total duration is not matching with what i imported. even i set the calender same as p3.1.



regards,


Jonald Calaycay
CAT Group Int’l (UAE)

3 replies

Oldest first
  1. 0
    Izam Zakaria ·
    How gap it is? Did ES equal each other
  2. 0
    Jonald Calaycay ·
    Hi Izam,

    The ES are all the same except the Gap is from 425 to 531.

    Thank you for the reply.



    Regards,


    Jonald

  3. 0
    Arnold Puy ·
    Hi Jonald,

    First of all welcome to Planning Planet.

    The Total Original Duration in Summary band calculated based on the "Default" calendar.

    In order to change the summary duration you must select the calendar that your current project used. To do that, go to --> Enterprise --> Calendars, select the calendar that your project currently used and mark the check box "Default".

    Regards,

    Arnold