about duration
In the Open Standard
Jason LIMember for 18 years 9 months
- Created
- 1
- 2
0
Dear all planer,
I have a test schedule use 7 days calendar in P6, activities under the WBS use 7days calendar, duration is 10days, SD Sep 3, FD Sep 12; when rollup to WBS SD & FD have no change, but duration change to 6 days, even I change the weekly hour to 56hrs at admin preference and user preference, still not working.
Thanks for your help
I have a test schedule use 7 days calendar in P6, activities under the WBS use 7days calendar, duration is 10days, SD Sep 3, FD Sep 12; when rollup to WBS SD & FD have no change, but duration change to 6 days, even I change the weekly hour to 56hrs at admin preference and user preference, still not working.
Thanks for your help