Skip to content

about duration

Jason LIMember for 18 years 9 months
Created
1
2
0
Dear all planer,
I have a test schedule use 7 days calendar in P6, activities under the WBS use 7days calendar, duration is 10days, SD Sep 3, FD Sep 12; when rollup to WBS SD & FD have no change, but duration change to 6 days, even I change the weekly hour to 56hrs at admin preference and user preference, still not working.

Thanks for your help

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi Jack,

    Go to Enterprise --> Calendars and change the default calendar to 7 days a week.

    Regards,

    Arnold

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?