Hi Victor,
is it possible in P6 to compute the no of resources needed only by just encoding a resource parameter.
for example a carpenter in formworks activity has a parameter of 2.8 manhours/sqm. i will only input the 2.8 then p6 will provide me the no of carpenter needed to complete that certain activity???is that possible or is p6 capable of that?
thanks & regards,
Pat
is it possible in P6 to compute the no of resources needed only by just encoding a resource parameter.
for example a carpenter in formworks activity has a parameter of 2.8 manhours/sqm. i will only input the 2.8 then p6 will provide me the no of carpenter needed to complete that certain activity???is that possible or is p6 capable of that?
thanks & regards,
Pat
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?