Relationships between projects

Sandy MathesonMember for 22 years
Created
2
3
0
I have 2 projects with relationship links which I want to remove (I know I can do it slowly 1 by 1!). Tried export to excel to flag as delete but relationships between projects did not export. These projects also have relationships to other projects so cannot copy and exclude. Any ideas for a quick method?

2 replies

Oldest first
  1. 0
    David Kelly ·
    Can you not copy/paste in one pass the group of projects that you want to retain the I/P relationships, and exclude the external relationships from that group?
  2. 0
    Arnold Puy ·
    Hi Sandy,

    The only fastest and easiest way which I used to do is to open the project and export it. You can now delete the original project and import the one you had exported.

    During the import, there is an "Update Project Options". Select "Modify", under the "Data Type: Project", select "Relationships to External Project" and select "Do not Import" and click OK.

    Let us know if the above steps works.

    I hope this helps.

    Regards,

    Arnold