Skip to content

At Completion cost

Sanjay RaoMember for 18 years 4 months
Created
1
3
0
Hi every one
we are updating the progress based on actual site progress. Some activity completed 95% and remaining 5 complete after say gap of 1 month (finishing works of that activity). My question is do we need to record that activity suspend & resume as i noticed very high cost to completion.
Note : I am using P 6.0 v
Thanks in advance.

1 reply

Oldest first
  1. 0
    Neal Walsh ·
    Hi Sanjay,

    I would always make use of the suspend / resume function during lengthy periods of no Activity to ensure no additional costs are incurred, providing the said Activity has in fact been suspended.

    Regards,

    Neil

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?